Indicators on Conditional meeting You Should Know
In spite of the disclaimer, the Idaho Supreme Court held which the subcontractor had encountered site conditions differing from Individuals indicated within the deal paperwork and which could not be seen for the duration of an affordable pre-bid site inspection. The subcontractor was awarded more payment.[5] Contractor encounters ground conditions